Refurbishment Updates
Droitwich Spa Leisure Centre
We’re excited to see improvements to Droitwich Spa Leisure Centre. This page is your go-to place for the latest refurbishment updates, including timelines, temporary changes, and what you can expect during the works.
We'll be keeping this page updated regularly, so please check back for the most up-to-date information as the refurbishment progresses.
Work is currently progressing as planned. This is the current estimated timeline, and we'll keep you informed with any updates as soon as we have them. See updates for Droitwich Spa Leisure Centre car park works below. Thank you for your patience and support.
Work is currently progressing as planned. This is the current estimated timeline, and we'll keep you informed with any updates as soon as we have them. See updates for Droitwich Spa Leisure Centre car park works below. Thank you for your patience and support.
on Monday 16th June, the last layer of tarmac is being laid. This will mean that there won’t be any access up to the football pavilion lane/pavilion car park for the day. Depending on the weather, it will re-open for our evening bookings. If it is hot, it will take longer to set, so our evening bookings might have to park on the rear car park and walk up to the pitches.
on Monday 16th June, the last layer of tarmac is being laid. This will mean that there won’t be any access up to the football pavilion lane/pavilion car park for the day. Depending on the weather, it will re-open for our evening bookings. If it is hot, it will take longer to set, so our evening bookings might have to park on the rear car park and walk up to the pitches.
Important Notice: Temporary Facility Closures from 21st July
As part of planned building improvements at Droitwich Spa Leisure Centre, some facilities will be temporarily unavailable from
Monday 21st July for approximately 20 weeks.
The following activities will be affected:
Badminton
Pickleball
Squash/Racketball
Virtual Classes
Indoor Netball (astro turf option may be available)
Indoor Football (astro turf option may be available)
Some of these facilities are still available at our Pershore and Evesham sites, so please get in touch if you'd like to explore those options.
We know how important the centre is to our members and we will do everything we can to minimise disruption. These upgrades will help us improve safety, comfort and your overall experience.
Thank you for your patience and continued support. We'll share updates throughout the works and confirm a re-opening date as soon as we can.
If you have any questions, please don’t hesitate to contact us.
Tarmac going down w/c June 2nd. Still on track to finish June 27th.






Phase 1 - Overflow Car Park (In Progress)
Timeline: Now until June 2025 (Phase 1)
The current overflow area is being converted into a permanent car park, adding 250+ extra spaces.
This will support parking for outdoor facilities, including pitch use and match days.
Expected completion: June 2025
Phase 2 – Front & Rear Car Parks
The front and rear car parks will be upgraded after the main building works are completed in 2026.
INDOOR CENTRE UPGRADES
Phase 1 – Starts End of July 2025
Refurbishment of internal areas begins, including the gym and fitness spaces.
Gym and fitness classes will temporarily move into the main hall, with a marquee added to provide extra space.
Squash, badminton and pickleball will be unavailable during this time.
The pool, health suite and café will remain open during this time.
Duration: approx. 20 weeks
Phase 2
(Follows Phase 1)
Swimming pool and health suite will close for refurbishment.
During this time, a new learner pool, café and brand new treatment rooms will be built.
Areas closed in Phase 1 will reopen once this phase begins.
Duration: approx. 20 weeks
Estimated timeline: February/March 2026
PROJECT COMPLETION
All refurbishment works are due to be completed by August – September 2026.
FAQs
-
The full refurbishment is expected to be completed by August - September 2026.
-
Phase 1 covers the conversion of the overflow area into a permanent car park with 250+ extra spaces, supporting outdoor facility use. This phase is currently in progress and due to be completed by June 2025.
-
These upgrades are scheduled for after the main building works are completed in 2026.
-
Indoor works begin at the end of July 2025.
-
They will be temporarily moved into the sports hall, with a marquee providing additional space.
-
Yes, squash, badminton and pickleball will be unavailable during Phase 1.
-
Yes, the pool, health suite, and café will remain open during Phase 1.
-
Phase 1 is expected to last approximately 20 weeks.
-
The swimming pool and health suite will close for refurbishment. A new learner pool, café, and treatment rooms will be built.
-
Yes, areas closed in Phase 1 (e.g. gym and fitness) will reopen once Phase 2 begins.
-
Yes, Little Al (who runs the café) will operate a mobile catering unit on-site for both customers and workmen.
-
Phase 2 will also last approximately 20 weeks, starting around February/March 2026.