Refurbishment Updates
Droitwich Spa Leisure Centre
We’re excited to see improvements to Droitwich Spa Leisure Centre and proud to be working with Wychavon District Council who are investing £15 million in to this refurbishment project. This page is your go-to place for the latest refurbishment updates, including timelines, temporary changes, and what you can expect during the works.
We'll be keeping this page updated regularly, so please check back for the most up-to-date information as the refurbishment progresses.
Work is currently progressing as planned. This is the current estimated timeline, and we'll keep you informed with any updates as soon as we have them. Thank you for your patience and support.
Work is currently progressing as planned. This is the current estimated timeline, and we'll keep you informed with any updates as soon as we have them. Thank you for your patience and support.
Important Updates
As part of planned improvement works, some facilities will be temporarily unavailable from Monday 14th July 2025 for approximately 20 weeks.
Here’s what you need to know:
Front car park is now closed. Please use the rear car park, including the new parking area.
Disabled parking is now available adjacent to the new reception entrance.
Internal building works have now begun.
The entrance, reception, customer service and physio room have been relocated to Studio 1 (rear of the building).
Badminton, Indoor Netball & Indoor Football are currently unavailable until Phase 2 of the project, which begins in 2026. Netball and football is still available on our astro turf, 3G or grass pitches.
The lift is no longer in use, but there is currently nothing available on the first floor.
Group exercise is now split between the marquee and sports hall, as Studio 1 is closed.
Studio 2 is now CLOSED.
Group exercise is now in the marquee or sports hall.
The gym has now relocated to the sports hall.
Dryside changing rooms are now closed. Please come ready for activity or use the wet side changing rooms.
Evesham & Pershore Leisure Centres are open as normal, so do get in touch with us if you’d like to explore alternative options.
We know how important the centre is to our members, and we’ll do everything we can to minimise disruption. You will also be guided and signposted where to go. These upgrades will improve your safety, comfort and overall experience.
We’ll keep you updated throughout and confirm the reopening date as soon as we can.
Please note that these dates are subject to change, but we’ll keep you updated with any changes.
Thanks for your patience and support. If you have any questions, please contact us.
Working in partnership with:
Tarmac going down w/c June 2nd. Still on track to finish June 27th.

















Phase 1 - Overflow Car Park (COMPLETED)
Timeline: Now until June 2025 (Phase 1) - COMPLETED
The current overflow area has been converted into a permanent car park, adding 250+ extra spaces.
This will support parking for outdoor facilities, including pitch use and match days.
New car park LED lighting has now been installed in all parking areas.
Expected completion: June 2025 - COMPLETED ON TIME ✅
Phase 2 – Front & Rear Car Parks
The front and rear car parks will be upgraded after the main building works are completed in 2026.
INDOOR CENTRE UPGRADES
Phase 1 – Starts End of July 2025
Refurbishment of internal areas begins, including the gym and fitness spaces.
Gym and fitness classes will temporarily move into the main hall, with a marquee added to provide extra space.
Squash, badminton and pickleball will be unavailable during this time.
The pool, health suite and café will remain open during this time.
Duration: approx. 20 weeks
Phase 2
(Follows Phase 1)
Swimming pool and health suite will close for refurbishment.
During this time, a new learner pool, café and brand new treatment rooms will be built.
Areas closed in Phase 1 will reopen once this phase begins.
Duration: approx. 20 weeks
Estimated timeline: February/March 2026
PROJECT COMPLETION
All refurbishment works are due to be completed by August – September 2026.
FAQs
-
Please use the rear car park, including the new car park area at the rear of the centre.
-
The full refurbishment is expected to be completed by August - September 2026.
-
Phase 1 covers the conversion of the overflow area into a permanent car park with 250+ extra spaces, supporting outdoor facility use. This phase is currently in progress and due to be completed by June 2025.
-
These upgrades are scheduled for after the main building works are completed in 2026.
-
Indoor works begin at the end of July 2025.
-
They will be temporarily moved into the sports hall, with a marquee providing additional space.
-
Yes, squash, badminton and pickleball will be unavailable during Phase 1.
-
Yes, the pool, health suite, and café will remain open during Phase 1.
-
Phase 1 is expected to last approximately 20 weeks.
-
The swimming pool and health suite will close for refurbishment. A new learner pool, café, and treatment rooms will be built.
-
Yes, areas closed in Phase 1 (e.g. gym and fitness) will reopen once Phase 2 begins.
-
Yes, Little Al (who runs the café) will operate a mobile catering unit on-site for both customers and workmen.
-
Phase 2 will also last approximately 20 weeks, starting around February/March 2026.